Riyadh Metro Expansion: Diriyah Extension and Expo Station
What is being added to the Riyadh Metro: the Diriyah extension, the Expo 2030 station, 94 extra trains and what is known about Line 7.
On this page
The Royal Commission for Riyadh City (RCRC) is extending the Metro's Red Line to Diriyah, building a new Expo station on the Yellow Line and buying 94 more trains. None of the new stations is open yet, so the current Metro map is still the one to travel by.
| Project | What is planned | When |
|---|---|---|
| Red Line extension to Diriyah | 8.4 km and 5 new stations | About 6 years from the January 2026 award |
| Expo station, Yellow Line | New station for the Expo 2030 site | Before Expo 2030 Riyadh |
| New trains | 94, taking the fleet from 183 to 277 | Deliveries from 2028 |
| Line 7 | Planned; one Diriyah station is designed to connect to it | No date from RCRC |
Red Line extension to Diriyah
The extension continues the Red Line west from King Saud University to the Diriyah Gate development (RCRC, in Arabic).
- Length: 8.4 km, of which 7.1 km is in deep tunnel and 1.3 km is elevated.
- Two stations at King Saud University: one for the medical city and health colleges, and one for the main university hall.
- Three stations in Diriyah, one of them designed as a future interchange with Line 7.
- Journey time: RCRC puts the trip from King Fahd Sports City, at the other end of the Red Line, to central Diriyah at no more than 40 minutes.
- Traffic: RCRC expects it to take about 150,000 vehicles off the road each day.
The contract was announced in January 2026 with a build time of about six years (Saudi Gazette). The tunnel boring machine was reported ready in July 2026 (Saudi Gazette). RCRC's names for the five stations were not in the sources we checked.
Until it opens, Diriyah has no Metro station. Plan on a taxi or a ride app for the last part of the trip.
Expo station on the Yellow Line
RCRC announced the start of work on Expo station on 15 November 2026 (RCRC). It is on the Yellow Line, which runs to King Khalid International Airport, and it will span King Salman Road between the Expo 2030 site to the east and new development areas to the west.
The building covers about 70,000 square metres under a 134 metre steel dome, and is designed for up to 19,000 passengers an hour. RCRC says it will be finished before Expo 2030 Riyadh. For getting to the airport today, see the Riyadh airport Metro guide.
94 more trains
On 13 October 2026 RCRC signed contracts worth about SAR 5.5 billion with Siemens and Alstom for 94 trains, with deliveries in phases from 2028 (RCRC, in Arabic). The announced capacity increases are:
| Line | More capacity |
|---|---|
| Red | 142% |
| Yellow | 116% |
| Blue | 60% |
| Orange | 27% |
| Purple | 16% |
Across the network the increase is 60%.
What is known about Line 7
RCRC confirms that a seventh line is planned and that one of the new Diriyah stations will connect to it (RCRC). We found no RCRC figure for its length, stations, cost or opening date.
Press reports go further. A Knight Frank estimate quoted by Arab News describes a 65 km line linking Qiddiya, King Salman Park, Diriyah Gate and New Murabba. Treat that as an outside estimate until RCRC publishes the route.
Frequently asked questions
Does the Riyadh Metro go to Diriyah?
Not yet. A five station Red Line extension is being built, with a build time of about six years from January 2026.
Is there a Metro station for Expo 2030?
One is under construction on the Yellow Line, due before the Expo opens.
When will Riyadh Metro Line 7 open?
RCRC has not published a date.
Related guides
Checked on 27 November 2026 against RCRC announcements and the linked news reports.